400-kV GIS Transmission Substations
Design and commissioning of the Punta de Palmas and Peonías substation complexes. Gas-insulated technology for a strategic energy transition.
Gas-insulated technology for a strategic energy transition.
Space constraints and the need for high corrosion resistance in industrial environments.
This project involved the engineering, procurement, fabrication, supply, installation, testing, and commissioning of two substations (Punta de Palmas Substation and Peonías Substation) located on the eastern and western coasts.
These substations are strategically located to facilitate the transition from overhead power lines to submarine and underground cables, helping to improve electricity service in the northwestern region of Lake Maracaibo and benefiting a population of more than 2,000,000 people. The initiative also includes the supply, installation, testing, and commissioning of two 400-kV lines in the eastern and western sections, connecting the substations to the existing line and dismantling the towers along the onshore section.
Technical Scope
Installation of SF6-insulated bay units
Configuration of busbars and transformers
SCADA Integration in Compliance with IEC 61850
Specialized Civil Construction Projects
Optimization of physical footprint and maintenance
No incidents reported.
The operation was carried out in accordance with corporate HSE policies and project-specific risk management plans.