400-kV Submarine Cable System — Lake Maracaibo

Engineering and deployment of 70 km of submarine and underground cable. An infrastructure milestone that ensures a stable power supply for more than 2 million people.

Location
Latin America
AWARDED IN
2017
Discipline
EPC / Engineering
Availability
24 / 7
Overview

A comprehensive solution, implemented with engineering precision.

Electrical interconnection in marine environments poses critical risks of power loss and environmental vulnerability, where any error in procurement or installation can jeopardize the energy stability of entire regions.

The scope of this project includes the engineering, procurement, fabrication, supply, installation, testing, and commissioning of a 400-kV submarine and underground cable system designed to cross beneath Lake Maracaibo and connect to sections of overland power lines on the eastern and western coasts.

We implemented a comprehensive Engineering, Procurement, and Construction (EPC) strategy for the deployment of 70 km of high-power cable. Thanks to our precision engineering and procurement management that meets international standards, we guarantee a resilient infrastructure that ensures the continuity of power supply under the most demanding marine conditions.

EPC Contract for a 70 KM 400 kV Submarine Cable

Technical Scope

Detailed engineering for XLPE cabling

Specialized international power of attorney services

Ampacity calculations and cathodic protection

Supervision of SAT and High-Voltage Testing

Regional Interconnection Security