Back to projects
circle-checkCompleted

Power Logistics: 300 MVA Autotransformer

Critical loading and transfer operation of a 333 MVA Siemens unit in a Latin American metropolis, completed without a single incident.

Location
Latin America
AWARDED IN
2021
Discipline
Logistics and Power Engineering
Availability
24 / 7
Overview

Critical loading and transfer operation, completed without any incidents.

An extremely challenging logistics operation where improper handling could cause internal structural damage. This project involved the loading, overland transport, and unloading of a 333 MVA, 230/138/24 kV Siemens three-phase autotransformer, with the heaviest component (the tank) transported from one substation to another. Completed in 2021, this initiative helped improve the electrical infrastructure of a major metropolitan city in Latin America.

Lifting and transport plan for heavy and oversized cargo, including impact monitoring.

Technical installation of accessories: bushings, radiators, oil conservators, and control panels.

Vacuum treatment, filtration, and filling of dielectric oil.

Diagnostic electrical tests: transformation ratio, insulation resistance, and power factor.

Our solution: Precision logistics engineering for immediate integration into the transmission network.
Mobilization of a 300 MVA Siemens Three-Phase Auto Transformer in a Major Metropolitan City

Technical Scope

Plan for lifting and transporting oversized loads

Technical assembly of hubs and boards

Vacuum oil treatment and filling

Resistance and Power Factor Measurement

Commissioning for the transmission network

No incidents were reported.

The operation was carried out in accordance with corporate HSE policies and project-specific risk management plans.